4.8MW Multi-Site Solar Rollout Across 862 Properties for AHO

A large-scale, multi-site rooftop solar rollout across 862 AHO properties, delivered with a strong focus on speed, safety, and respectful tenant communication.

4.8MW Multi-Site Solar Rollout Across 862 Properties for AHO

A large-scale, multi-site rooftop solar rollout across 862 AHO properties, delivered with a strong focus on speed, safety, and respectful tenant communication.

The Challenge
Delivering a rollout of this scale across 862 individual residential sites required a delivery model built for volume, speed, and consistency. Each property presented unique access conditions, roof types, and delivery constraints, requiring strong scheduling discipline, repeatable quality controls, and safe work methods across every site.

Just as importantly, this program required clear and respectful tenant communication to minimise disruption, support smooth access, and maintain a positive experience for residents. Alongside these delivery requirements, meaningful Aboriginal participation outcomes needed to be embedded into the project through genuine employment pathways, training support, mentoring, and culturally safe workplace practices.

The Solution

TSP Energy delivered a structured, high-volume rollout solution designed specifically for rapid multi-site delivery. Our team implemented a standardised approach to engineering, scheduling, installation, and quality checks to maintain consistent outcomes across every site. Safety was prioritised from planning through to completion, supported by disciplined onsite controls and documentation.

Tenant engagement was embedded into our delivery process from the outset, ensuring residents were informed, access requirements were coordinated professionally, and communication remained consistent across all sites.

In parallel, TSP Energy integrated Aboriginal participation outcomes into project delivery by supporting employment and training opportunities, helping develop skills and confidence on the job, and creating pathways for long-term careers in the renewable energy sector.


Engineering & Project Management

TSP Energy’s engineering and project management teams coordinated the full delivery lifecycle across all sites, ensuring each installation met programme timelines, compliance requirements, and quality expectations. This included site verification, system design, installation coordination, commissioning, and handover documentation. Through proactive scheduling and strong stakeholder management, our team supported efficient site access and maintained consistent workmanship across the full portfolio. All works were delivered under a safety-first culture with clear onsite controls, structured supervision, and a focus on doing the job properly every time.


Bringing It Together

The Aboriginal Housing Office Solar Rollout is a 4.86 MW, multi-site program delivered across 862 properties throughout NSW, with 5.64 kW installed at each site. The portfolio is expected to generate approximately 7,800 MWh of clean electricity annually, avoiding about 5300 tonnes of CO2 annually. The project is helping reduce grid reliance and improve sustainability outcomes across AHO’s housing assets. TSP Energy’s rollout model was built for speed of delivery without compromising safety, quality, or compliance. Through strong programme management and clear tenant communication, installations were completed efficiently while minimising disruption for residents. This combination of performance, safety, and respectful engagement ensured a smooth delivery experience and consistent results across a large and diverse portfolio.

4.8MW
Greater Sydney and Regional NSW
7800 MWh Annual Generation
Government
2024-2025
Government
  • Government Solar
  • Multi Site

4.8MW Multi-Site Solar Rollout Across 862 Properties for AHO

A large-scale, multi-site rooftop solar rollout across 862 AHO properties, delivered with a strong focus on speed, safety, and respectful tenant communication.

The Challenge
Delivering a rollout of this scale across 862 individual residential sites required a delivery model built for volume, speed, and consistency. Each property presented unique access conditions, roof types, and delivery constraints, requiring strong scheduling discipline, repeatable quality controls, and safe work methods across every site.

Just as importantly, this program required clear and respectful tenant communication to minimise disruption, support smooth access, and maintain a positive experience for residents. Alongside these delivery requirements, meaningful Aboriginal participation outcomes needed to be embedded into the project through genuine employment pathways, training support, mentoring, and culturally safe workplace practices.

The Solution

TSP Energy delivered a structured, high-volume rollout solution designed specifically for rapid multi-site delivery. Our team implemented a standardised approach to engineering, scheduling, installation, and quality checks to maintain consistent outcomes across every site. Safety was prioritised from planning through to completion, supported by disciplined onsite controls and documentation.

Tenant engagement was embedded into our delivery process from the outset, ensuring residents were informed, access requirements were coordinated professionally, and communication remained consistent across all sites.

In parallel, TSP Energy integrated Aboriginal participation outcomes into project delivery by supporting employment and training opportunities, helping develop skills and confidence on the job, and creating pathways for long-term careers in the renewable energy sector.


Engineering & Project Management

TSP Energy’s engineering and project management teams coordinated the full delivery lifecycle across all sites, ensuring each installation met programme timelines, compliance requirements, and quality expectations. This included site verification, system design, installation coordination, commissioning, and handover documentation. Through proactive scheduling and strong stakeholder management, our team supported efficient site access and maintained consistent workmanship across the full portfolio. All works were delivered under a safety-first culture with clear onsite controls, structured supervision, and a focus on doing the job properly every time.


Bringing It Together

The Aboriginal Housing Office Solar Rollout is a 4.86 MW, multi-site program delivered across 862 properties throughout NSW, with 5.64 kW installed at each site. The portfolio is expected to generate approximately 7,800 MWh of clean electricity annually, avoiding about 5300 tonnes of CO2 annually. The project is helping reduce grid reliance and improve sustainability outcomes across AHO’s housing assets. TSP Energy’s rollout model was built for speed of delivery without compromising safety, quality, or compliance. Through strong programme management and clear tenant communication, installations were completed efficiently while minimising disruption for residents. This combination of performance, safety, and respectful engagement ensured a smooth delivery experience and consistent results across a large and diverse portfolio.

4.8MW
Greater Sydney and Regional NSW
7800 MWh Annual Generation
Government
2024-2025
Government
  • Government Solar
  • Multi Site